SCC Grants PATH's Withdrawal from VA


The Virginia State Corporation Commission has officially granted PATH's request to withdraw its application in Virginia. Here is a link to the SCC Order.

The SCC ordered that the company include the following information in any future application, should the company choose to re-apply:

  • PJM Interconnection's Regional Transmission Expansion Plans of 2010 or later and PJM's 2010 or later Reliability Pricing Model auction
  • Updated load flow analyses in the form requested for this case (which showed no need for the PATH line in 2014).
  • An analysis of changes in circumstances, including changes in generation, demand response, and energy efficiency resources.
  • The PATH Project's original routes (including routes that do not impact Virginia) consistent with the information provided regarding other proposed and alternative routes